View budget vs actual

Compare your planned budget to actual spending.

Budget vs actual report

  1. Go to Budget & Finance
  2. View the main dashboard showing:
    • Budget — Planned amount
    • Allocated — Committed (linked issues)
    • Spent — Actual costs
    • Variance — Budget – spent (+ or -)
CategoryBudgetSpentVariance
Engineering$600k$550k+$50k (under)
Design$200k$220k-$20k (over)
Total$800k$770k+$30k (under)

Drill down by team

  1. Click a team budget
  2. See that team’s budget vs. actual breakdown

Drill down by area

  1. Click a team
  2. Click an area
  3. See that area’s budget vs. actual

Budget vs. actual reports often show:

  • Month 1: $50k spent of $200k budget (25%)
  • Month 2: $95k spent of $200k budget (47%)
  • Month 3: $180k spent of $200k budget (90%)

This trend helps you forecast if you’ll go over budget.

Analyze variance

If you’re over budget:

  1. See Manage budget overruns

If you’re under budget:

  1. Consider reallocating funds to other areas
  2. Or confirm the budget is still aligned with plans

Export for reporting

  1. Click Export in Budget & Finance
  2. Choose Budget vs Actual
  3. Download CSV or PDF

Share with leadership or stakeholders.

Set variance alerts

Some companies set alerts:

  • Alert if spending exceeds 85% of budget
  • Alert if spending is on track to exceed budget by quarter-end

Check Settings > Alerts or Notifications if configured.