Category: Support

Support and help

  • View budget vs actual

    Compare your planned budget to actual spending.

    Budget vs actual report

    1. Go to Budget & Finance
    2. View the main dashboard showing:
      • Budget — Planned amount
      • Allocated — Committed (linked issues)
      • Spent — Actual costs
      • Variance — Budget – spent (+ or -)
    CategoryBudgetSpentVariance
    Engineering$600k$550k+$50k (under)
    Design$200k$220k-$20k (over)
    Total$800k$770k+$30k (under)

    Drill down by team

    1. Click a team budget
    2. See that team’s budget vs. actual breakdown

    Drill down by area

    1. Click a team
    2. Click an area
    3. See that area’s budget vs. actual

    Budget vs. actual reports often show:

    • Month 1: $50k spent of $200k budget (25%)
    • Month 2: $95k spent of $200k budget (47%)
    • Month 3: $180k spent of $200k budget (90%)

    This trend helps you forecast if you’ll go over budget.

    Analyze variance

    If you’re over budget:

    1. See Manage budget overruns

    If you’re under budget:

    1. Consider reallocating funds to other areas
    2. Or confirm the budget is still aligned with plans

    Export for reporting

    1. Click Export in Budget & Finance
    2. Choose Budget vs Actual
    3. Download CSV or PDF

    Share with leadership or stakeholders.

    Set variance alerts

    Some companies set alerts:

    • Alert if spending exceeds 85% of budget
    • Alert if spending is on track to exceed budget by quarter-end

    Check Settings > Alerts or Notifications if configured.

  • Track spending and allocations

    Monitor how your team’s spend aligns with budget.

    Issues can be tagged with cost categories (optional):

    1. Create an issue
    2. In the detail panel, set:
      • Budget area — Which budget this work belongs to
      • Estimated cost (optional) — How much this issue will cost
    3. Click Save

    View spending by team

    1. Go to Budget & Finance
    2. Click a team budget
    3. See:
      • Budget amount — The cap
      • Allocated — Money committed to active work
      • Spent — Actual costs incurred
      • Remaining — Budget – allocated – spent

    Track by area

    Click a team budget to see its areas:

    • Backend API area: $80k budget, $65k spent, $15k remaining
    • Frontend area: $70k budget, $52k spent, $18k remaining

    Track by person

    Click an area to see its members:

    • Alice: $30k budget, $22k spent, $8k remaining
    • Bob: $40k budget, $38k spent, $2k remaining

    Update actual spending

    1. In Budget & Finance, click an area or person
    2. Click + Add spending or Log expense
    3. Enter:
      • Amount — How much was spent
      • Category — What it was spent on
      • Date — When it was spent
      • Notes — Details
    4. Click Save

    Bulk update spending

    If you have many expenses:

    1. Export a CSV template from Budget & Finance
    2. Fill in amounts and categories
    3. Upload the CSV
    4. Spending updates automatically

    See allocated vs. spent

    • Allocated — Issues estimated at $X for this budget
    • Spent — Actual expenses logged for this budget

    Allocated is useful for forward-looking planning. Spent is for tracking actual costs.

  • Set up multi-level budgets

    Budgets in Forest exist at multiple levels: project, team, area, user, and discipline.

    Budget hierarchy

    Project Budget
    ├── Team Budget (e.g., Engineering, Design)
    │   ├── Area Budget (e.g., Frontend, Backend)
    │   │   └── User Budget (e.g., Alice, Bob)
    └── Discipline Budget (e.g., by functional area)
    

    You don’t have to use all levels—start simple and add complexity as needed.

    Create a project budget

    1. Go to Budget & Finance
    2. Click + New Budget or New Project Budget
    3. Enter:
      • Name — Usually your project name
      • Total amount — Annual or quarterly budget
      • Currency — USD, EUR, etc.
    4. Click Create

    The project budget is now your top-level container.

    Create team budgets

    1. In Budget & Finance, click your project budget
    2. Click + New Team Budget or + Team
    3. Enter:
      • Name — Team name (e.g., “Engineering”)
      • Budget amount — How much this team can spend
    4. Click Create

    Team budgets nest under the project budget.

    Create area budgets

    Areas break down team budgets further:

    1. Click a team budget
    2. Click + New Area Budget or + Area
    3. Enter:
      • Name — Area name (e.g., “Backend API”)
      • Budget amount
    4. Click Create

    Area budgets nest under team budgets.

    Create user budgets

    User budgets track spending by person:

    1. Click an area budget (or team budget)
    2. Click + New User Budget or + Person
    3. Enter:
      • Name — Person’s name or ID
      • Budget amount — Their allocation
    4. Click Create

    Discipline budgets

    Discipline budgets organize spending by functional area:

    1. Create discipline budgets similar to team budgets
    2. Assign people to disciplines in Settings > Disciplines
    3. Budget & Finance shows discipline-level spending

    Budget per quarter

    Some teams set budgets by quarter:

    BudgetQ1Q2Q3Q4
    Engineering$150k$150k$200k (hiring)$200k
    Design$50k$50k$50k$50k

    Create separate budget entries for each quarter, or set a total annual budget.

  • Scenario-based budget planning

    Test hiring and staffing scenarios with budget impact.

    Create a budget scenario

    1. Go to Scenario Planning
    2. Create a staffing scenario (e.g., “Hire 2 engineers Q3”)
    3. Switch to Budget & Finance within that scenario
    4. See how budget changes with the new headcount

    Example

    Baseline: 15 engineers, $600k annual budget Scenario: Hire 2 engineers mid-Q3

    • Q1–Q2: $300k (baseline)
    • Q3: $325k (4.5 months original + 1.5 months new hires)
    • Q4: $350k (all 17 people)
    • Total: $825k vs. $600k budget
    • Delta: Need $225k additional budget

    Compare budget across scenarios

    1. Go to Scenario Planning
    2. View multiple staffing scenarios
    3. Create a comparison:
    ScenarioHeadcountAnnual CostVariance
    Baseline15$600k
    Hire 2 eng17$825k+$225k
    Hire 3 eng18$950k+$350k
    Attrition (-2)13$500k-$100k

    Make hiring decisions

    Use budget scenarios to approve hiring:

    • “We can hire 2 engineers in Q3 for +$225k”
    • “Or defer hiring to Q4”
    • “Or hire 1 now, 1 in Q4”

    Commit scenario to budget

    Once you’ve committed a staffing scenario:

    1. The budget automatically reflects new headcount
    2. Update your budget in Budget & Finance to match
    3. Communicate the new budget to stakeholders

    Adjust budget for scenarios

    1. Create a scenario
    2. Add/remove headcount
    3. Update budget in Budget & Finance > scenario mode
    4. See financial impact side-by-side with staffing

    Monitor actuals against scenario budget

    Once a scenario becomes baseline:

    Forecast remaining spend for the year

    Track spending against the scenario budget

    Adjust actuals as hires ramp up

  • Manage budget overruns

    When spending exceeds your budget, take corrective action.

    Identify overruns

    1. Go to Budget & Finance
    2. Look for red indicators (over budget)
    3. Click to see details:
      • How much you’re over
      • Which categories exceeded budget
      • Overage %

    Analyze the cause

    Ask:

    • Did scope expand (more work than planned)?
    • Were estimates inaccurate (work cost more)?
    • Was spending higher than expected (vendor costs)?

    Corrective actions

    Option 1: Request budget increase

    1. Calculate the overrun amount
    2. Document why (scope changes, estimate misses, inflation)
    3. Request approval from leadership to increase budget
    4. Update budget amounts in Budget & Finance

    Option 2: Reduce scope

    1. Review pending work in Board or Backlog
    2. Defer low-priority work to next quarter
    3. This reduces estimated costs

    Option 3: Reduce spending

    1. Negotiate vendor contracts
    2. Optimize cloud spend
    3. Pause non-essential subscriptions

    Option 4: Reallocate from other budgets

    1. Check if other budgets are under-running
    2. Transfer budget from areas that don’t need it
    3. Use it to cover the overrun

    Prevent future overruns

    1. Estimate conservatively — Add 10–20% buffer to uncertain work
    2. Track spending regularly — Don’t wait until quarter-end
    3. Forecast ahead — Use Budget forecasting and trends to predict overruns early
    4. Communicate early — Tell leadership if you see an overrun coming

    Communicate with stakeholders

    Send a summary:

    “Engineering is on track to exceed budget by 15% ($90k over). This is due to scope expansion on the payment system project. We recommend either increasing budget or deferring the notification system to Q4.”

  • Budget forecasting and trends

    Predict future spending based on current trends.

    1. Go to Budget & Finance
    2. Look for the Trends or Forecast chart
    3. See monthly spending over time:
    Q1:  $50k (month 1) → $90k (month 2) → $130k (month 3)
    Q2:  $60k (month 4) → $100k (month 5) → $140k (month 6) → projected $180k (month 7)
    

    Forecast future spending

    1. Click Forecast or Trending
    2. See a projection of where you’ll end at quarter-end or year-end

    If the trend continues:

    • Current spending: $500k through month 9
    • Projected year-end: $650k
    • Budget: $600k
    • Projected overrun: $50k

    Adjust forecast parameters

    Some forecasts let you adjust:

    1. Burn rate — Spending velocity per week/month
    2. Headcount changes — Adding/removing people affects spend
    3. Project timeline — If a project extends, spending extends

    Change parameters to see how they affect forecast.

    Early warning

    Use forecasting to catch overruns early:

    1. If forecast shows a $50k overrun in month 8, you have time to:
      • Request budget increase
      • Defer work
      • Reduce scope
    2. Don’t wait until month 12 to react

    Incorporate scenarios

    If you’re using Scenario Planning:

    1. Create a budget scenario for each staffing scenario
    2. See how hiring affects your spend
    3. Use this to make hiring decisions

    See Scenario-based budget planning.

    Share forecasts

    Export your forecast:

    Use in planning meetings

    Click Export in Trends

    Share with leadership

  • Model hiring and headcount changes

    Test headcount and staffing changes in a scenario without affecting your baseline.

    Add a team member to a scenario

    1. Go to Scenario Planning and open a scenario
    2. Go to Settings > Teams (within the scenario)
    3. Click a team
    4. Click + Add Member
    5. Enter:
      • Name — e.g., “Alice (new hire)”
      • Time allocation — % (default 100%)
    6. Click Add

    The scenario now includes this new person, increasing team capacity.

    Set an anticipated start date

    1. Click the new scenario member
    2. Enter Start date — When they join
    3. Adjust time allocation per quarter if they ramp up gradually
    4. Click Save

    Before their start date, their capacity is 0. After, they contribute full capacity.

    Model partial ramping

    Scenario members often ramp up gradually:

    • Q1: 50% (onboarding)
    • Q2: 75% (ramping)
    • Q3: 100% (full contribution)
    • In the scenario, adjust the member’s time allocation per quarter
    • Each quarter can have a different allocation
    • Capacity Planning recalculates utilization with the ramp-up

    Remove a team member

    1. In the scenario, go to Settings > Teams
    2. Click the team
    3. Find the member
    4. Click Remove or set allocation to 0%
    5. Click Save

    The scenario now reflects the loss of this capacity.

    Model attrition

    1. Duplicate the baseline scenario
    2. Remove team members (or reduce their allocation)
    3. See how capacity is impacted
    4. Plan how to backfill

    Model department expansion

    1. Create a new scenario
    2. Add multiple team members
    3. Set their start dates
    4. See how capacity grows over time
    5. Use this to forecast what projects you can take on

    Budget impact

    Adding headcount affects budget. See Scenario-based budget planning for financial scenarios.

  • Create and manage scenarios

    Scenarios let you test “what-if” staffing changes without affecting your real baseline data.

    Create a scenario

    1. Go to Scenario Planning
    2. Click + New Scenario
    3. Enter:
      • Name — e.g., “Hiring 2 engineers Q3”
      • Description (optional) — Context for your team
    4. Click Create

    The scenario is created as a copy of your current baseline (headcount, team structure, capacity).

    Edit a scenario

    1. Click the scenario to open it
    2. Make changes:
      • Add team members
      • Remove team members
      • Adjust time allocation
      • Adjust time off
    3. Changes are saved automatically in the scenario only

    Your baseline remains unchanged.

    View scenario capacity

    1. In the scenario, go to Capacity Planning
    2. See how utilization changes with your hypothetical staffing

    For example, adding 2 engineers may reduce utilization from 95% to 70%.

    Compare scenarios

    1. Go to Scenario Planning
    2. View side-by-side cards for multiple scenarios
    3. Compare headcount, capacity, and costs

    Delete a scenario

    1. Click the scenario
    2. Click Delete
    3. Confirm

    Deleted scenarios cannot be recovered.

    Duplicate a scenario

    1. Click the scenario menu (•••)
    2. Click Duplicate
    3. Edit the duplicate for a new scenario

    This is useful when testing multiple variations.

    Scenario naming conventions

    Use clear, descriptive names:

    ✅ “Offshore expansion”

    ❌ “Scenario 1”

    ✅ “Hiring 2 engineers Q3”

    ✅ “Attrition case (2 departures)”

  • Compare scenarios

    Review multiple scenarios to decide which staffing plan is best.

    View your scenarios

    1. Go to Scenario Planning

    All scenarios appear as a list, showing:

    • Scenario name
    • Status (Draft, Submitted, Finance Approved, CFO Approved, Official)
    • Description
    • Project name and year
    • Submitted by (name and date)

    Each scenario also shows a status badge indicating where it is in the approval workflow.

    View scenario details

    1. Click View on a scenario

    The scenario detail view opens, showing:

    • Budget Tracker — Team structure, headcount, costs, and time allocations
    • Budget breakdown — By team, area, discipline, and user
    • Discipline submissions — Individual discipline budget submissions (for finance reviewers)
    • Status information — Current approval stage and next steps

    Compare scenarios manually

    Since there’s no built-in side-by-side comparison view, compare scenarios by:

    Method 1: Open in multiple browser tabs

    1. Right-click View on Scenario 1 → Open in new tab
    2. Go back and right-click View on Scenario 2 → Open in new tab
    3. Switch between tabs to compare budgets and headcount

    Method 2: Screenshot and document

    1. View Scenario 1 and note key numbers:
      • Total headcount
      • Key budget amounts (by team/discipline)
      • Costs by quarter
    2. View Scenario 2 and take screenshots
    3. Create a comparison document (spreadsheet or document) with key metrics

    Method 3: Create a summary spreadsheet

    Build your own comparison outside the app:

    MetricBaselineHiring (2 eng)Attrition (2 lost)
    Headcount151713
    Q2 Budget$420k$450k$380k
    Q3 Budget$420k$455k$380k
    Q4 Budget$420k$480k$380k
    Annual Cost$1.68M$1.845M$1.52M

    Analyze what matters

    When comparing scenarios, consider:

    • Cost difference — What’s the financial impact of each option?
    • Headcount timeline — When do hiring or attrition changes take effect?
    • Quarterly variance — Do costs and headcount shift by quarter?
    • Approval status — Which scenarios are still in draft vs. approved?
    • Risk profile — Which scenario is most conservative?

    Discuss with stakeholders

    Once you’ve reviewed multiple scenarios:

    1. Share key numbers with your team or leadership
    2. Explain the tradeoffs (cost vs. capacity, speed vs. risk)
    3. Get feedback on which direction to pursue

    Make a decision

    Once stakeholders approve a scenario:

    1. See Commit scenarios to baseline to make it official

    Note on scenario approval

    Scenarios follow an approval workflow:

    1. Draft — Created and being edited
    2. Submitted — Awaiting Finance review
    3. Finance Approved — Finance approved, awaiting CFO approval
    4. CFO Approved — CFO approved, can be locked as Official
    5. Official — Locked as the company’s baseline budget

    Only official scenarios become the baseline for capacity planning and budgeting.

  • Commit scenarios to baseline

    Once you’ve decided on a staffing plan, commit the scenario to make it your new baseline.

    When to commit

    Commit a scenario when:

    • Your team has approved the staffing changes
    • Hiring has been approved by leadership
    • Attrition is imminent and confirmed
    • You want the scenario to become your actual baseline

    Commit a scenario

    1. Go to Scenario Planning
    2. Click the scenario you want to commit
    3. Click Commit to baseline
    4. Review the changes:
      • New team members to add
      • Team members to remove
      • Allocation changes
    5. Click Confirm

    The scenario is now your baseline. All views (Board, Capacity, Budget) reflect the new structure.

    What happens to the committed scenario?

    After committing:

    • The scenario is archived or replaced
    • The baseline is updated
    • Historical baseline is preserved (for reference)

    What about other scenarios?

    Other scenarios are not affected. They still show their hypothetical staffing based on the old baseline.

    If needed, you can:

    1. Delete old scenarios
    2. Create new scenarios based on the updated baseline

    Undo a commitment

    If you committed a scenario by mistake:

    1. Contact your project admin or company admin
    2. They may be able to restore the previous baseline from backup
    3. Or, manually revert team changes in Settings > Teams

    There is no “undo scenario commit” button—it’s intentional (to prevent accidental reverts).

    Next steps

    Create new scenarios for next planning cycle

    Communicate the changes to your team

    Update your financial budget if applicable (see Scenario-based budget planning)

    Re-plan your roadmap with the new capacity